Is it possible to conduct agricultural activities while building a wind farm?

Czy prowadzenie działalności rolnej przy budowie farmy wiatrowej jest możliwe?
  • As Sevivon's expert emphasizes, the construction phase of a wind farm usually lasts from 1 to a year and a half.
  • Is it possible to conduct agricultural activities while building a wind farm? Brygida Węsierska, project manager – project implementation, Sevivon says yes, but certain conditions must be met.
  • The construction of a wind farm involves not only difficulties in carrying out field work, but also the risk of soil disturbance or damage to drainage systems.
  • The farmer should also be financially protected in the event of damage occurring during the investment in a wind farm.

Brygida Węsierska, project manager – project implementation, Sevivon, was present at the Power Field conference in Gniew. She shared with us her knowledge about the most important stages of building a wind farm from the farmer's point of view.

Such a large investment may cause a lot of difficulties not only for the investor, but also for the farmer who cannot interrupt agricultural work during the installation of wind turbines.

Elimination of the 10H rule. Wind farms even closer to residential buildings

read more

Elimination of the 10H rule. Wind farms even closer to residential buildings

How long does the construction phase of a wind farm in rural areas take?

As the Sevivon expert emphasizes, the construction phase of a wind farm usually lasts from 1 to a year and a half.

Of course, it may take longer, depending on the size and scope of such a renewable energy investment. When implementing such a large renewable energy investment, dialogue with the property owner and the experience of the investor, such as Sevivon, are crucial – notes Brygida Węsierska, project manager – project implementation, Sevivon.

How can you tell if a farmer is working with professionals building wind farms?

So how should cooperation work between a farmer leasing land for renewable energy sources and a company building a wind farm? After the way of communication with employees implementing such a large investment.

Farmers are always well informed by our employees, not only when construction work on the wind farm will start. We inform farmers about the exact start dates of individual construction stages and when the deliveries of turbine components to the leased agricultural land are planned – emphasizes Brygida Węsierska, project manager – project implementation, Sevivon. – All this to ensure that every farmer cooperating with us experiences the least possible inconvenience in conducting agricultural activities when we implement our RES investment.

\

What difficulties does a farmer leasing land for a wind farm have to prepare for?

The construction of a wind farm involves not only difficulties in conducting field work, but also the risk of soil disturbance or damage to drainage systems.

We do not hide the fact that each implementation of a large renewable energy investment will cause disadvantage to farmers in carrying out agricultural work, especially during the season. The access of construction machines becomes problematic during sowing and subsequent harvesting, especially when heavy traffic increases and construction work on the wind farm intensifies. However, we professionally try to minimize all these disadvantages to our clients. It is thanks to good organization and close cooperation with farmers that we are able to facilitate their work in the field, while at the same time we are carrying out intensive work related to the construction of the wind farm – emphasizes Brygida Węsierska, project manager – project implementation, Sevivon.

Moreover, as the Sevivon expert emphasizes, a well-informed farmer knows when the individual stages of wind turbine construction works will be carried out and the difficulties associated with them. This knowledge allows him to better plan work in the field during construction.

How long does it take from signing the land lease agreement to launching the wind farm?

read more

How long does it take from signing the land lease agreement to launching the wind farm?

How to minimize the risk of damaging drainage in the field or disturbing the soil during the construction of a wind farm?

Disturbances of soil structures or risk of damage to drainage in fields. This is what can happen on a wind farm construction site that requires laying hundreds of kilometers of cable lines. How can these risks be reduced?

Before we start building wind turbines, we locate cable lines and connections at the border of agricultural plots. When it comes to drainage, first of all we contact farmers and agree with them where exactly they are located in the field, because not all information can be found on the map. Here, the key to success is successful cooperation and communication with farmers before construction begins – emphasizes Brygida Węsierska, project manager – project implementation, Sevivon.

As the Sevivon expert emphasizes, such good cooperation with the farmer allows you to minimize damage to his agricultural land, so that he can continue his agricultural activities as far as possible even during the construction of the wind farm.

We don't mix up the soil structure; soil humus is separated from slough. We are talking to the land owner about where we should leave the excess excavated material and how to deal with it – emphasizes Brygida Węsierska, project manager – project implementation, Sevivon.

Power Fields, or what is the plan for farmers for cheap energy and low-emission food?

read more

Power Fields, or what is the plan for farmers for cheap energy and low-emission food?

The lease agreement should protect farmers in the event of damage resulting from the construction of a wind farm

Therefore, the farmer should feel fully financially secured even in the event of unforeseen damage during the construction of a wind farm. Therefore, if damage occurs to drainage or agricultural crops, the farmer is financially protected against them with a contract for the lease of land for renewable energy from Sevivon.

Additionally, this agreement obliges us – both before the start of construction and at its individual stages – to prepare detailed documentation. During construction, all ground damage and repairs are carefully recorded; we prepare separate descriptions and documentation. The farmer takes an active part in describing the damage and signing repair reports. Therefore, we make sure that it is comprehensively secured even in the event of unforeseen damage during the construction of the wind farm – summarizes Brygida Węsierska, project manager – project implementation, Sevivon.